In short
- Savings are consumption that did not happen: they are calculated as adjusted baseline minus measured consumption, plus or minus adjustments.
- IPMVP options: A and B isolate the retrofit, C uses whole-facility meters, D a calibrated simulation.
- Baseline, variables, meters and adjustment method are fixed in the M&V plan before the work starts.
- Metered white-certificate projects in Italy need at least 12 months of pre-retrofit data, sampled at least daily.
What is IPMVP, and why can't savings be measured directly?
IPMVP (International Performance Measurement and Verification Protocol) is the international measurement and verification (M&V) protocol of the Efficiency Valuation Organization (EVO): it defines the terms, principles and methods used to quantify energy, water and demand savings. The current edition is IPMVP Core Concepts 2022, supported by application guides such as the one on uncertainty assessment (EVO 10100-1:2019).
Savings are the absence of consumption: no instrument can measure them. You measure consumption before and after the retrofit and compare the two on a like-for-like basis. If production grew or the winter was colder, a bill-to-bill comparison understates the effect; in the opposite case it inflates it.
The protocol asks for results that are as accurate as the project value justifies, complete, conservative (when in doubt, do not overstate), consistent, relevant and transparent, so that an outside reviewer can rebuild them.
How are savings calculated: baseline, reporting period and adjustments
With the general IPMVP equation:
Savings = (Baseline period energy − Reporting period energy) ± Routine adjustments ± Non-routine adjustments
- Periods: the baseline comes before the retrofit and covers a full operating cycle, from maximum to minimum consumption; the reporting period follows the retrofit and lasts at least one normal cycle.
- Independent variables ("operating variables" in the Italian GSE's wording): production, degree-days, operating hours. They drive the routine adjustments, calculated with a model, often a regression.
- Static factors: floor area, equipment served, weekly shifts, product type. If they change, a non-routine adjustment is needed, engineered case by case.
- Interactive effects: effects outside the measurement boundary, such as LED lamps reducing internal heat gains and so changing heating and cooling. They must be estimated or excluded with a stated reason.
Avoided energy or normalised savings?
Avoided energy answers the question "how much would I have used this year without the retrofit?": the reporting period's variables, fed into the baseline model, give the adjusted baseline, from which measured consumption is subtracted. It is the most common approach, but the result depends on the conditions of the year. Normalised savings bring both periods to an agreed fixed set of conditions, such as a typical weather year: they can be compared year on year and with forecasts, but need a full cycle of post-retrofit data.
What are IPMVP Options A, B, C and D, and when should each be used?
The measurement boundary changes: A and B isolate the equipment being retrofitted, C takes in the whole facility, D replaces missing data with a calibrated simulation.
| Option | What is measured | When | Example | Cost and limits |
|---|---|---|---|---|
| A – Retrofit isolation, key parameters | The key parameters before and after; the others are estimated, with the source documented | Predictable savings, stable estimates | LEDs: power measured, hours estimated from shift patterns | Lowest; the error of the estimates must be stated |
| B – Retrofit isolation, all parameters | The equipment's energy and its variables, short-term or continuous | Variable loads or savings | Drive on a pump, meter on the feeder | Dedicated meters; more certain result |
| C – Whole facility | Main meters, over complete years (12, 24 or 36 months) | Many interacting measures | Plant-wide energy management programme | With monthly data, savings must exceed about 10% of the baseline; static factors must be tracked |
| D – Calibrated simulation | A model calibrated on bills or measurements, normally 12 consecutive months | No baseline: new buildings, extensions | New department with no history | Most demanding: needs skilled modellers |
The 10% figure is an IPMVP rule of thumb: with monthly data, smaller savings are lost in the variation the model cannot explain; with hourly or daily data and more accurate models, smaller savings can be verified too.
What goes into a measurement and verification plan?
The M&V plan sets out how savings will be calculated and must be approved by the parties before the retrofit; to claim IPMVP adherence it must cite the edition of the protocol and name who approves it. It covers:
- the measures, their intent and expected savings, with the reference audit;
- option, measurement boundary and interactive effects;
- baseline: period, consumption, independent variables, static factors, anomalies corrected;
- reporting period and reporting frequency;
- adjustment method: models, coefficients, statistical indices (R², CV(RMSE)) and the range of variables over which the model is valid;
- energy prices used to value the savings;
- meters (type, accuracy, metering points, calibration, lost data), responsibilities, expected accuracy, budget and quality assurance.
Under Option A the estimates and their sources must also be listed, and periodic inspections scheduled. Where to place meters is covered in the guide to industrial energy monitoring.
Every savings figure carries uncertainty from instruments, model and sampling: the plan states it, using the methods of EVO's uncertainty guide or ASHRAE Guideline 14-2023. If the savings are not large compared with the uncertainty, lengthen the period, use denser data or narrow the boundary.
IPMVP and ISO standards
ISO 50015:2014 gives principles for M&V of an organisation's energy performance, ISO 17741:2016 general rules for the savings of a project, and ISO 50006:2023 the method for energy performance indicators (EnPIs) and energy baselines (EnBs). IPMVP adds the detail for the individual project.
From the field
On feeders with a variable speed drive, the meter must measure true active power with distorted currents, not estimate it from current and power factor, and it must sit upstream of the drive: otherwise the drive's losses fall outside the boundary and the savings look larger than they are. Check the current transformers too: after the retrofit they often run at a small fraction of their rating, where error grows.
Caution
Installing meters and current transformers in a switchboard, even for a temporary campaign, is electrical work for skilled or instructed persons under CEI 11-27 and EN 50110-1.
Worked example: a drive on a pump, verified with Option B
Hypothetical figures, only to show the method. A 55 kW fixed-speed pump, throttled by a valve, serves a cooling circuit; the retrofit adds a variable speed drive with pressure control.
- Option: the plant uses about 4,000 MWh a year and the expected saving is around 100 MWh, 2–3%: too little for Option C on monthly data. Option B is used.
- Metering: an active energy meter upstream of the drive, installed 12 months before the work and read daily. Independent variable: tonnes produced; static factor: the loads served by the circuit.
- Baseline model (regression over 300 production days): E = 600 kWh + 2.0 kWh/t × P, valid within the production range observed.
| Step | Calculation | Result |
|---|---|---|
| Measured baseline | 300 days, 60,000 t (the model gives 300,000 kWh) | 301,200 kWh |
| Reporting period | 300 days, 66,000 t (+10%), measured energy | 214,000 kWh |
| Adjusted baseline (routine) | 300 × 600 + 2.0 × 66,000 = 180,000 + 132,000 | 312,000 kWh |
| Non-routine adjustment | new load on the circuit from month eight: what it would have added at fixed speed (documented calculation) | +4,000 kWh |
| Avoided energy | 312,000 + 4,000 − 214,000 | 102,000 kWh (32% of 316,000) |
| Value | 102,000 kWh × €0.18/kWh (hypothetical price fixed in the plan) | €18,360 a year |
| Naive comparison | 301,200 − 214,000, no adjustments | 87,200 kWh (€15,696) |
The naive comparison understates the result by 14,800 kWh, about €2,660 a year, because production grew by 10%; had production fallen, it would have overstated it.
Which option suits which efficiency measure?
It depends on how much the savings vary and what can be measured:
| Measure | Option | What to measure | Watch out for |
|---|---|---|---|
| LED lighting | A | Power before and after, operating hours | With occupancy sensors the hours change: measure them (B) |
| Drives on pumps and fans | B | Energy upstream of the drive, production or flow | Metering with distorted currents |
| Compressed air leaks | B | Compressor energy, air delivered or pressure | Leaks come back: meter continuously |
| Compressor replacement | B | Specific consumption in kWh/m³ | Air demand varies between shifts |
| Heat recovery | B, or C on gas | Heat recovered and boiler consumption | Interactive effects on the boiler |
| Power factor correction | A | Currents before and after, kvarh on the bill | The benefit is mostly financial |
| Process changes | B or C | Energy per unit produced | Product changes are static factors |
| Site programme or ISO 50001 | C | Main meters, production, degree-days | Complete years, a log of changes |
| New department with no history | D | Simulation calibrated on post-retrofit metering | Modelling skills |
Power factor correction mainly cuts reactive energy charges and losses in cables and transformers; the kWh saved are few and are estimated from the currents (see the guide to reactive energy and power factor correction). When a measure also improves power quality, part of the benefit lies in avoided downtime, failures and penalties: value it separately, as the guide to the costs of power quality explains.
Where are verified savings required in Italy?
In metered white-certificate projects, in energy performance contracts (EPCs) and, for audit purposes, in Transition 5.0 tax credits already granted. Position as at 17 November 2026.
White certificates: metered projects
The rules are the MASE (environment and energy ministry) decree of 21 July 2025 (Official Journal of 11 September 2025) and the new GSE operating guide, approved by MASE in July 2026; projects approved earlier follow the decree of 11 January 2017. One white certificate (TEE) is worth one tonne of oil equivalent (toe) of additional primary energy savings.
- In a metered project (progetto a consuntivo, PC) savings are measured before and after the retrofit under a measurement programme approved by the GSE: metering points, instruments and accuracy class, algorithm, handling of lost data.
- Baseline: consumption and operating variables over at least twelve months, sampled at least daily, unless a shorter period is shown to be representative; savings are calculated for the same service delivered, normalising the conditions.
- Timing and thresholds: the project must be submitted, or announced in advance, before the work starts; a PC must save at least 10 toe in its first twelve months; savings are reported yearly.
- Applicants include ESCos certified to UNI CEI 11352 and organisations that have appointed an energy management expert (EGE) certified to UNI CEI 11339 or hold ISO 50001 certification.
The decree does not refer to IPMVP, but the logic of baseline and normalisation is the same.
Transition 5.0 and the 2026 hyper-depreciation
Transition 5.0 (art. 38 of Decree-Law 19/2024) covers investments from 1 January 2024 to 31 December 2025 that cut the consumption of the production facility by at least 3%, or of the processes concerned by at least 5%, against the previous financial year and net of changes in production and external conditions: a routine adjustment, in IPMVP terms. An independent assessor certifies ex ante the achievable reduction and ex post that the investments were made. The funds are exhausted (MIMIT directorial decree of 6 November 2025), but the GSE also checks the reduction in consumption: keep the measurements and calculations.
For investments from 1 January 2026 to 30 September 2028, the 2026 Budget Law (Law 199/2025, art. 1, paragraphs 427-436) introduced hyper-depreciation, which replaces the 4.0 and 5.0 tax credits. MIMIT's description requires a sworn appraisal and an accounting certificate and sets out no energy-saving threshold: M&V is not a requirement here, but it remains the way to prove the return on the investment.
Energy performance contracts (EPCs)
Under an EPC the supplier is paid according to the agreed efficiency improvement, verified throughout the contract (Directive (EU) 2023/1791). For public bodies, Annex 8 of Legislative Decree 102/2014 lists among the minimum elements the guaranteed savings, clear provisions for quantifying and verifying them, and the procedure for handling changes such as energy prices and intensity of use: in practice, an M&V plan. The Italian government's EPC handbook (DIPE, 2022) points to IPMVP as the reference for the baseline; UNI CEI 11352:2014 sets the requirements for ESCos offering services with guaranteed results.
Which mistakes make savings impossible to prove?
Almost always decisions made, or missed, before the work:
- Short or unrepresentative baseline: less than a full cycle or, under Option C, 9, 13 or 18 months that weight the seasons wrongly; stoppages and breakdowns left uncorrected.
- Ignored variables: bill against bill while production or weather changed.
- Meters installed after the retrofit: no Option B and, for white certificates, no twelve-month baseline.
- Wrong boundary: metering downstream of the drive, interactive effects ignored.
- Adjustments not agreed: a new line, an extra shift, a product change; if the method is not in the plan, it becomes a negotiation.
- Model used out of range and persistence not checked: leaks that come back, drives left in bypass.
How much to spend on M&V, and who carries the risk?
IPMVP says M&V costs should be small relative to the value of the savings and proportionate to the consequences of getting them wrong. What is at stake is the annual saving over the verification years, plus whatever depends on it: white certificates, EPC fees. In the example, about €18,000 a year justifies a dedicated meter and a few hours of analysis a month, not a calibrated simulation.
In guaranteed-performance contracts the plan decides who carries which risk: production volumes stay with the client, through routine adjustments, while equipment performance sits with the supplier. IPMVP suggests measuring the factors the supplier controls and estimating the rest.
Poweremp supports companies on the technical side: consumption baselines and KPIs, efficiency plans with estimated benefits, metering systems including MID-certified meters, continuous monitoring and verification of savings after the retrofit, through its energy consulting and incentive support services. Sworn appraisals are signed by qualified professionals.
Frequently asked questions
Is IPMVP mandatory in Italy?
No, it is a voluntary protocol: it becomes binding when a contract refers to it. White certificates follow the measurement programme approved by the GSE.
How long should the baseline be?
A full operating cycle, so a year if consumption depends on the seasons. Metered white-certificate projects need at least twelve months of data sampled at least daily.
Are energy bills enough to verify a saving?
Only under Option C, and only if the saving exceeds about 10% of baseline consumption; estimated readings must be flagged. A single measure almost always needs a dedicated meter.
Who can sign off the savings?
IPMVP does not certify plans: it asks for the approver to be named and recommends a qualified professional, such as a CMVP. In Italy, EGEs certified to UNI CEI 11339 and ESCos certified to UNI CEI 11352 are the recognised figures.
Sources and standards
- EVO, IPMVP and IPMVP Core Concepts 2022; Uncertainty Assessment for IPMVP (EVO 10100-1:2019).
- ASHRAE Guideline 14-2023; ISO 50015:2014; ISO 17741:2016; ISO 50006:2023.
- MASE, decree of 21 July 2025 on white certificates (Official Journal no. 211 of 11 September 2025); GSE, operating guide for white certificates (2026). In Italian.
- Decree-Law 19 of 2 March 2024, art. 38, converted by Law 56/2024. In Italian.
- MIMIT, Transition 5.0 funds exhausted (7 November 2025) and New Transition 5.0 Plan – hyper-depreciation; Law 199 of 30 December 2025. In Italian.
- Legislative Decree 102 of 4 July 2014, annex 8; Directive (EU) 2023/1791, art. 2 and annex XV.
- DIPE, PPP and energy performance contracts (EPC) from A to Z (2022, in Italian).
- UNI CEI 11352:2014; UNI CEI 11339; CEI 11-27; EN 50110-1.