In short

  • The bill tells you how much you use; monitoring tells you where and when: base load, compressed-air leaks, idling machines, quarter-hour peaks.
  • Mandatory energy audits in Italy (Legislative Decree 102/2014) must rest on measurements: ENEA requires metering 40% to 85% of the consumption of the main activities, depending on site size.
  • Meter from the top down: main incomer, functional areas, then the significant energy uses.
  • kWh per unit produced misleads when output changes: you need a regression baseline (ISO 50006).
  • Before analysing, check wiring, CT ratios, clocks and data gaps.

Why monitor consumption when you already get a bill?

Because the bill gives the monthly total per time band, not where or when the energy was used. The costs you can cut sit in the detail:

  • Base load: whatever stays on at night, at weekends and during holidays, such as compressors feeding nothing but leaks, extraction fans, air handling, lighting, machines on standby.
  • Compressed air: according to the US Department of Energy (DOE), leaks in a poorly maintained system can waste 20–30% of compressor output, against 5–10% where leaks are found and fixed regularly.
  • Idling machines between batches.
  • Peaks: without a limiter set to a contracted power, the per-kW components of the Italian distribution tariff are charged on the month's highest average power over a fixed quarter-hour (ARERA's TIT, art. 1). One quarter-hour with overlapping start-ups is enough.

With suitable instruments, the same points also watch power factor and reactive energy, harmonics and voltage dips. Reactive charges aside, what disturbances cost (losses, downtime, scrap, failures) never shows up on the bill: see the guide to power quality costs.

Is monitoring mandatory? Energy audits and ENEA's monitoring plan

There is no general duty to install sub-meters, but for companies subject to the mandatory energy audit, monitoring is required in practice: the audit must rest on measured data and, after the first one, on a monitoring plan.

  • Who: large enterprises, except those using less than 50 toe a year, and energy-intensive companies in the Italian relief scheme, whatever their size (Legislative Decree 102/2014, art. 8).
  • When: by 5 December 2015, then every four years, carried out by certified parties (ESCOs, certified energy managers, auditors) and uploaded to ENEA's Audit102 portal. Large enterprises whose ISO 50001 system includes a compliant audit are exempt; energy-intensive companies must implement at least one measure identified or adopt ISO 50001.
  • On what data: Annex 2 requires up-to-date, measured and traceable operational data and, for electricity, load profiles.

ENEA's guidelines (second edition, 2021) split the consumption of each energy carrier into main activities (the process), auxiliary services (which turn one carrier into another for the process, such as the compressed-air plant) and general services (lighting, HVAC, offices). For each area they set a minimum share of metered consumption, relative to the utility meter:

Site consumption (toe/year)Main activitiesAuxiliary servicesGeneral services
over 10,00085%50%20%
5,600 – 6,69965%30%20%
2,300 – 3,39950%15%10%
100 – 1,19940%5%5%

The full table has ten bands; carriers below 10% of site consumption are excluded (no more than 10% in total) and sites below 100 toe may be. If the coverage is not reached, the audit must include a programme to reach it by the next one; a company first obliged in year n must have monitoring running from 1 January of year n+3.

What about Directive (EU) 2023/1791?

The recast Energy Efficiency Directive (art. 11) ties the obligations to average consumption over the previous three years: above 85 TJ a year (about 23.6 GWh of total energy), a certified energy management system by 11 October 2027; above 10 TJ (about 2.8 GWh), for companies without one, an audit by 11 October 2026 and then at least every four years, with an action plan. Transposition was due by 11 October 2025: as of November 2026 no Italian decree with these thresholds appears to have been published, and ENEA applies art. 8 of Legislative Decree 102/2014. Check the status.

Which standards guide monitoring: ISO 50001, ISO 50006, EN 16247?

None sets a number of meters: they require metering whatever is needed to control the significant uses.

StandardWhat it asks of monitoring
EN ISO 50001:2018 (+A1:2024), energy management systemsIdentify the significant energy uses (SEUs) and plan the collection of energy data (clause 6.6): relevant variables, indicators, accurate and repeatable measurements
ISO 50006:2023, indicators (EnPIs) and baselines (EnBs)Choice of indicators, normalisation, statistical models, static factors
ISO 50015:2014, measurement and verification of energy performancePrinciples for demonstrating improvement; for individual measures IPMVP is widely used
EN 16247-1:2022 and parts 2–4, energy auditsEnergy audit method

Where should the meters go?

From the top down, following consumption: one main meter per energy carrier, then functional areas and departmental switchboards, then the loads that weigh most.

Main meter Main activities Auxiliary services General services level B level C level C level C Line 1 Furnace Compressors Chillers Lighting Offices Level D: individual loads and significant energy uses metering point; offices estimated by difference
Metering hierarchy following ENEA's scheme: cover the heaviest loads first and estimate the rest by difference.
  • Main incomer: your own meter downstream of the utility meter gives real-time data and the reference for checking every other meter.
  • Functional areas: switchboards rarely match the areas. If the production switchboard also feeds the department lighting, meter that feeder separately and assign it to general services.

To choose the loads (compressors, chillers, furnaces, air handling, lighting), estimate each one's annual consumption (power × load factor × hours) and meter from the most energy-hungry down, until you reach the required coverage or the remainder is small and stable; loads that vary with production or can be controlled come first. The same applies to other carriers: gas, heat, compressed-air flow for kWh per normal cubic metre.

What should be measured, and how accurately?

At every point, active and reactive energy, average power over the quarter-hour and power factor; where needed, voltages, harmonics and events.

QuantityWhat it is for
Active energy imported and exportedConsumption, indicators, costs per F1, F2, F3 time band
Average power over 15 minutesLoad profile, peaks, committed power
Reactive energy and power factor, with inductive or capacitive signReactive charges, power factor correction checks
Per-phase voltages and currentsLoad per phase, unbalance
THD, voltage eventsDistortion, dips, overvoltages

Accuracy classes. Static meters: IEC 62053-21:2020 (classes 0.5, 1 and 2) and IEC 62053-22:2020 (0.1S, 0.2S and 0.5S, for transformer-operated meters). MID meters (Directive 2014/32/EU, Annex V): classes A, B and C, needed when the data has legal-metrology value. Multifunction devices: IEC 61557-12, with energy uncertainty derived from the IEC 62053 classes.

A meter is not a power quality analyser: dips, harmonics and comparison with EN 50160 call for the IEC 61000-4-30 methods (see power quality analysis). Where that data is needed too, an analyser such as ALADIN measures at the same point energy, signed reactive energy, power factor, unbalance, THD and voltage events.

Current transformers. Both meter and CT count: for metering, CTs of class 0.5 or 0.5S are used (IEC 61869-2); the "S" classes stay accurate at low currents too. Choose the ratio on the actual current, not on the breaker: an oversized CT runs at a small fraction of its rating, where the error is largest. On existing installations, split-core CTs or Rogowski coils are used.

Caution

Fitting CTs and meters in live switchboards is work for skilled or instructed persons under CEI 11-27 and EN 50110-1. Never open-circuit the secondary of a CT carrying current: use terminal blocks with shorting links.

Communication and interval. Switchboards are dominated by Modbus RTU (RS-485) and Modbus TCP, read by a gateway; heat, water and gas meters often use M-Bus (EN 13757); hard-to-wire points can use radio networks such as LoRaWAN, which suit 15-minute readings. Read the energy registers too: if communication drops, the missing period can be recovered by difference. The base interval is the fixed quarter-hour (:00, :15, :30, :45): Italian second-generation low-voltage smart meters record quarter-hour curves (ARERA resolution 87/2016/R/eel), committed power is calculated on the quarter-hour, and since 1 January 2025 imbalances have been settled over 15 minutes. Diagnosis needs one-minute data or finer.

How are energy performance indicators (EnPIs) and baselines built?

An energy performance indicator (EnPI; ENEA calls it IPE) relates energy to what drives it; the baseline tells you how much you would have used under the same conditions. Without normalisation, kWh per piece gets worse as soon as output drops.

  • Indicators: kWh per tonne or per piece, kWh per m² in buildings, kWh per normal cubic metre of compressed air.
  • Relevant variables (ISO 50006): change routinely and move consumption, such as output, degree-days, operating hours.
  • Static factors: do not normally change, such as shift pattern, floor area, product type; if they do, the baseline must be adjusted.

The most common model is a linear regression on baseline-period data: E = a + b·P (plus c·DD if heating or cooling matters), where a is the consumption independent of output and b the consumption per unit produced.

Example with hypothetical numbers

Twelve months of data give E = 120 MWh + 0.45 MWh/t × P; on average 400 t and 300 MWh a month, i.e. 750 kWh/t. After an intervention, a month with 300 t uses 248 MWh:

Baseline (monthly average)Month after the intervention
Output400 t300 t
Measured consumption300 MWh248 MWh
Simple kWh/t750827 (+10%)
Consumption expected by the model300 MWh120 + 0.45 × 300 = 255 MWh
Deviation—−7 MWh (−2.7%)

The simple ratio points to a 10% deterioration, the model to a 2.7% improvement. The difference is the fixed 120 MWh, which weighs more as output falls: reducing it is the first target of monitoring. Check that the coefficients make physical sense, that the residuals show no pattern and that the data cover every operating condition; the statistical criteria are in the guide to IPMVP.

How do you read load profiles, idle consumption and peaks?

On a typical week: the night and holiday minimum is the base load, the Monday ramp shows the start-ups, the month's highest quarter-hour sets the committed power.

  • Base load: compare it with what genuinely has to stay on. With hypothetical numbers, 50 kW that could be switched off over 88 non-productive hours a week (168 minus 5 days × 16 hours) come to about 229,000 kWh a year, roughly €34,000 at €0.15/kWh.
  • Peaks: staggering start-ups lowers the maximum; load-management systems forecast the average of the current quarter-hour and shed deferrable loads before the threshold.
  • Deviations: compare measurement and baseline every day or week; the cumulative sum of deviations (CUSUM) shows when a drift began. Useful alarms: night or holiday consumption above a threshold, capacitive reactive energy with the plant stopped.
  • Reports: costs, indicators and savings for management; profiles and alarms for the engineers.

Poweremp's energy monitoring service connects standard and MID meters and power analysers to a cloud platform with dashboards, KPIs, anomaly detection, costs per time band and automated reports.

How do you make sure the data can be trusted?

With checks at commissioning and then every month: wrong data produces waste or savings that do not exist.

  1. Wiring: under load, positive active power on every phase and a plausible power factor. A CT on the wrong phase or fitted backwards shifts the angle without any alarm: see the "From the field" box in the guide to power factor correction.
  2. Ratios and units: CT ratio set once only, in the meter or in the software; consistent W or kW, Wh or kWh; import and export signs.
  3. Monthly balances: main meter against utility meter; main meter against the sum of the sub-meters plus the estimated share.
  4. Clocks: NTP synchronisation, storage in UTC; the day the clocks change has 92 or 100 quarter-hours.
  5. Gaps and asset register: values rebuilt from the energy registers and flagged as estimates; a record of the loads each meter covers and of every change, since changes are static factors.

From the field

If the sub-meters add up to more than the main meter, or a department draws power with the plant stopped and nobody can explain why, check the configuration first, then the installation: a CT ratio applied twice, a CT on another feeder's cable, exported energy added to imported energy. A balance check in the first week saves months of analysis on bad data.

What savings does monitoring reveal, and how are they verified?

Monitoring saves nothing on its own: it shows where to act and measures the result.

  • Compressed air: with production stopped and all air users closed, for a load/unload compressor leakage is T × 100 / (T + t) per cent of capacity, where T is time on load and t time unloaded (DOE). If nobody uses air at the weekend, the compressor room's power is the cost of the leaks.
  • Pumps and fans: with variable-speed drives instead of throttling valves and dampers, the affinity laws make power vary with the cube of speed; at 80% speed about half the power is needed in theory (0.8³ ≈ 0.51); with static head the gain is smaller.
  • Schedules: air handling, lighting and machines programmed to actual shifts.
  • Power factor correction sized on data: see the guide to reactive energy.

In the audits submitted to ENEA for the 5 December 2025 deadline, the compressed-air measures identified had an average investment of about €37,700 and a simple payback of 3.5 years; those in the "General" area (monitoring, organisation, training, ISO 50001) about €29,800 and 4.5 years, without incentives; ENEA notes that this area also helps identify further measures. The return on monitoring is the savings it uncovers.

To demonstrate a saving, compare consumption after the measure with what the baseline predicts under the same conditions: that is measurement and verification of savings (IPMVP), which also documents the results many incentive schemes require.

Frequently asked questions

How many sub-meters are needed?

As many as it takes to cover the significant energy uses; for companies subject to the mandatory audit, at least ENEA's shares per functional area. A meter on a small, stable load adds little.

Is the distributor's data enough?

It is useful for the main incomer and for checking your own meters: second-generation smart meters record each quarter-hour and are read remotely every day. But they say nothing about departments and do not arrive in real time.

Do I need a MID meter?

Only where the data has legal-metrology value, such as splitting costs between separate parties. For internal monitoring it is not mandatory.

Does ISO 50001 require meters to be installed?

It sets no number: it requires a data collection plan for significant uses, relevant variables and indicators, with accurate and repeatable measurements. In practice the significant uses have to be metered.

Sources and standards

Facing a similar problem in your installation?

Tell us what is happening: we help you work out what to measure, where and for how long, before you change anything in the installation.