In short

  • Start with the question (compliance, diagnosis, baseline for an investment): it decides points, duration and instrument.
  • IEC 61000-4-30 methods, 2025 edition: Class A or S; Class B no longer exists.
  • Point of supply plus suspect feeders: two synchronised points separate grid and plant.
  • At least one week; longer, or continuously, for rare events.
  • Check connections, CT/VT ratios and the clock straight away: one error spoils the whole campaign.

When do you need a power quality analysis, and what question should it answer?

You need one when there is a problem to explain (stoppages, electronics failures, tripping, deteriorating capacitors), when the supply voltage has to be documented, or before an investment that changes the installation. These are three different analyses: write the question down before choosing the instrument.

QuestionWhere to measureFor how longInstrument
Compliance: does the voltage meet EN 50160 or the ARERA limits?Point of supplyAt least one weekClass A if the results must stand up to third-party scrutiny
Diagnosis: why does the line stop or the capacitors fail?Point of supply, suspect feeders and sensitive loads, togetherUntil the problem has recurred several timesClass S, with a synchronised clock
Baseline and verification of power factor correction, filters, UPS, PVMain switchboard and the point of interventionA typical week, before and afterSame instrument, same settings

An analysis without a question produces hundreds of charts and no decision. A good question closes with a yes or a no: "do the line 3 stoppages coincide with voltage dips from the grid?". Symptoms and disturbances are summarised in the guide to power quality disturbances.

Which instrument do you need: Class A or Class S?

You need a power quality analyser that applies the IEC 61000-4-30 methods: Class A when results must be comparable between instruments and hold up with third parties, Class S for surveys and diagnosis. The edition in force, Ed. 4.0 of October 2025, updated the event and rapid voltage change methods and removed Class B, which had already been relegated to an informative annex in 2015.

AspectClass A (advanced)Class S (surveys)
Voltage uncertainty±0.1% of the declared input voltage±0.5%
Frequency uncertainty±10 mHz±50 mHz
ClockExternal synchronisation (GPS, radio or network time signals): ±20 ms at 50 HzNo synchronisation required; drift up to ±5 s per day
150-cycle (3 s) aggregationContiguous intervals, aligned with the 10-minute tickGaps between intervals allowed
Typical useContracts, disputes, compliance checksSurveys, statistics, diagnosis

Values of the 2015 edition as reported by manufacturers and technical articles; the standard in force is what counts.

IEC 61000-4-30 describes methods; requirements and tests for the instruments (PQI-A and PQI-S, fixed or portable) are in IEC 62586-1:2017 and IEC 62586-2:2017+AMD1:2021. A "Class A" claim should be backed by a test report to IEC 62586-2: ask for it. Class A or S functions can also be built into meters and protection relays.

If flicker or transients matter

Flicker requires the IEC 61000-4-15 flickermeter (2010 edition), which computes Pst over 10 minutes and Plt over 2 hours; without it, an EN 50160 assessment is incomplete (see flicker).

Impulsive transients have microsecond fronts (the IEC 61000-4-5 test impulse rises in 1.2 µs), so sampling in the MHz range is needed. One manufacturer, for example, samples mains quantities at 80 kS/s and transients at 1 or 20 MS/s depending on the model. If you suspect impulsive overvoltages, choose an instrument with a stated transient function (see overvoltages and transients).

Instrument safety

The instrument and its accessories must comply with IEC 61010-1 and IEC 61010-2-030 (2023 edition), with a suitable measurement category: CAT IV at the origin of the installation (point of supply, meter, main protection), CAT III on distribution switchboards, busbars and feeders. The accessory with the lowest category is what counts.

Where should the instruments be installed?

At the point of supply or, for MV customers, the secondary of the MV/LV transformer; then on the main LV switchboard and the feeders that matter for the question. Guidance on locations, pre-monitoring site surveys and thresholds is in an informative annex of IEC 61000-4-30 (Annex B in the 2015 edition).

  • Point of supply: sees the grid plus the sum of internal disturbances; it is the reference for EN 50160 and ARERA.
  • Feeders of disturbing loads: drives, rectifiers, welders, furnaces, capacitor banks.
  • Supply of the loads that stop: PLCs, drives, sensitive machines; this is where you measure what the machine experiences.

At MV you measure through inductive VTs, designed for 50 Hz metering and protection: their accuracy for harmonics and transients needs checking (IEC TR 61869-103).

Why two measurement points are better than one

Two synchronised instruments, at the point of supply and on the suspect feeder, tell a grid disturbance from an internal one. Dips are the clearest case: if the current rises as the dip starts, the cause is downstream of the measurement point (motor start, internal fault); if voltage and current fall together, it is upstream.

Downstream origin (plant) Upstream origin (grid) U I U I current rises voltage and current fall together time time
RMS voltage (U) and current (I) at the same point during a dip: on the left a motor start downstream, on the right a fault in the grid.

It is a rule of thumb, not proof: confirm it with the second point and with the distributor's records (see voltage dips).

Harmonics are harder. The direction of harmonic active power, often used to decide who is "polluting", is not reliable: a study in IEEE Transactions on Power Delivery showed that it depends on the phase angle between the sources more than on their size. You work by comparison instead: voltage THD with the plant stopped and in production, current spectra of the feeders, distortion with and without power factor correction.

How long should you measure?

At least one full week for an EN 50160 assessment; for a diagnosis, until the problem has recurred several times; continuously if it is rare or intermittent.

IEC 61000-4-30 computes quantities over 10-cycle windows (200 ms at 50 Hz) and aggregates them into 150-cycle (3 s), 10-minute and 2-hour values. A week is 1,008 ten-minute values. Intervals containing a dip, swell or interruption are flagged and can be excluded from the statistics, so the same event does not count twice.

  • Production cycle: shifts, weekends, restarts, periodic operations, standby generator or PV operation; for voltage and loads, different seasons too.
  • Rare events: in 2024 the ARERA average was 3.86 severe MV-origin dips per MV customer per year: a week may see none.
  • Before and after an intervention: weeks with similar production, same instrument, same points and settings.

Intermittent problems call for continuous monitoring with fixed instruments. ALADIN, for example, stays in the switchboard, samples voltages and currents at 16 kHz per channel, records every event with time, duration and residual voltage together with the current drawn just before it, and computes 10-minute values for EN 50160. It is not Class A certified, but it builds up months of data against which stoppages can be correlated.

How do you set up the instrument before starting the recording?

With a checklist: almost every error is made in the first hour and discovered at the end of the campaign.

  1. Declared voltage (Udin): 230 V phase-to-neutral or 400 V phase-to-phase at LV; at MV the VT secondary voltage, with the VT ratio. Thresholds are computed from this value.
  2. Configuration: three-phase with or without neutral, ARON (two-wattmeter) connection with two CTs and two VTs, single-phase. If it is wrong, the values look plausible but are false.
  3. CTs and VTs: ratios entered, arrow on clamps and sensors towards the load, each clamp on the phase of its own voltage. Flexible sensors (Rogowski coils) wrap around large busbars without saturating, but they do not measure DC, are poorly suited to small currents and should be closed with the joint away from the conductor.
  4. Phase sequence: L1-L2-L3 positive, checked on the instrument.
  5. Event thresholds: dip below 90% of Udin, swell above 110%, interruption below 5%, as in EN 50160; current triggers to capture motor starts.
  6. Clock: GPS or NTP on the instrument, with the PLC and SCADA clock offsets noted; without a common time base you cannot correlate events, alarms and instruments.
  7. Memory and supply: enough space for the whole campaign; instrument powered by battery or from a source that stays live during interruptions, or the decisive event is lost.
  8. Log: diagram of the points, photos of the connections, settings, times, production events noted by staff.

Caution

Connecting instruments in a live switchboard is live or near-live work: in Italy it is reserved for skilled or instructed persons, also authorised for live working (PEI) where the work is live, under CEI 11-27 (2025 edition) and CEI EN 50110-1, with PPE suited to the arc-flash risk as well and protected voltage leads. Never open the secondary of a CT in service: it develops dangerous voltages, so short it first.

Which measurement errors spoil an analysis, and how do you spot them in the data?

A wiring error raises no alarm: you recognise it from inconsistencies in the data, to be checked in the first hours.

ErrorWhat it looks like in the dataCheck
Loose neutral or voltage referenceFloating voltages, events of opposite sign on different phasesMultimeter on the same terminals (see EN 50160)
Reversed CTNegative active power on one phasePositive active power on every phase of a load drawing power
CT on the wrong phaseAngle shifted by 120°, absurd power factor on one phaseClamp-to-voltage pairing (see reactive energy)
Wrong CT or VT ratioPower and energy a multiple or a fraction of the real valuesComparison with the meter's kWh and kvarh over the same period
Wrong declared voltageNo events at all, or bursts of events and every statistic out of rangeUdin consistent with the configuration
Unsynchronised clockEvents offset by a constant time from the alarmsComparison with a switching operation at a known time
Point downstream of a UPS or stabiliserThe grid looks perfectPosition of the point relative to the loads to be protected

From the field

The most useful check is made right after installation: positive active power on every phase, a plausible power factor, voltages matching the multimeter, correct phase sequence. A few minutes save a week of data; and a campaign with doubtful connections cannot be "corrected" at the desk: it has to be repeated.

How do you read the results of a power quality analysis?

Starting from the question: first the events and whether they coincide with the problems, then the statistics compared with the right limit for that point.

Events

Each event has a time, duration, residual or maximum voltage and the phases involved. Classify the dips in the EN 50160 residual voltage–duration table and line them up against the stoppage times: the events that stopped the line and those that did not mark out its real ride-through capability. The current before, during and after the event shows whether the origin is internal or in the grid.

Statistics

  • Voltage: share of 10-minute values within the band; for the ARERA check at LV in Italy, 207–253 V with no statistical margin (see EN 50160).
  • Harmonics: voltage THD and individual harmonics at the 95th percentile, against EN 50160 at the point of supply and the IEC 61000-2-4 classes inside the plant; for current, TDD (see harmonics).
  • Unbalance: negative- to positive-sequence voltage ratio, within 2% for 95% of the values under EN 50160 (see unbalance).
  • Valid data: a week with many gaps or flagged intervals is not representative.

What a good report contains

  • question and answer in one sentence, single-line diagram with the points;
  • instruments (model, class, calibration), configuration, CT/VT ratios, thresholds;
  • period, valid and flagged data, measurement anomalies;
  • statistics with the limit and standard used at each point, events correlated with stoppages and currents;
  • conclusions with their level of confidence, interventions in order of priority, verification measurement.

What happens after the analysis?

You choose the intervention according to what was found and what the problem costs, then you measure again.

FindingNext stepFurther reading
Grid dips that stop production linesImmunity of control circuits, drive settings, targeted UPSVoltage dips
High voltage THD, failing capacitorsResonance check, detuned power factor correction, filtersHarmonics
Overvoltages, electronics failuresNeutral check, surge protective device coordinationOvervoltages and transients
Voltage or current unbalanceRedistribution of single-phase loadsVoltage unbalance
Flicker above limitsIdentify the fluctuating load, check the short-circuit powerFlicker
RCD or breaker tripsLeakage currents, inrush, harmonicsNuisance tripping
Low power factor, reactive chargesPower factor correction sized on measured profilesReactive energy
Voltage out of limits at the point of supplyRequest a supply voltage check from the distributorEN 50160

Every intervention is justified by the cost it avoids (stoppages, scrap, failures, charges): how to estimate it is explained in the guide on the cost of power quality problems. If it also cuts consumption, the savings are demonstrated with the IPMVP protocol. Poweremp's Power Quality audit follows this sequence: site survey, measurement campaign at the most significant points, report with the causes, interventions verified through continuous monitoring.

Frequently asked questions

Do you always need a Class A instrument?

No: you need one when the result has to stand up to third-party scrutiny, for example with the distributor. For a diagnosis, Class S with a synchronised clock is enough. The recorder that the distributor installs at the customer's request and cost must also comply with CEI EN 50160 and CEI EN 61000-4-30 (TIQD, art. 55).

Is a multimeter or a clamp meter enough?

No: they give instantaneous readings and record neither events lasting a few hundredths of a second nor weekly statistics.

Can it be done without stopping production?

Yes, and it should be done during normal production: skilled or instructed persons connect the instrument with the switchboard live, using clamps or flexible sensors.

What should be prepared before the campaign?

Single-line diagram, transformer data, a list of large loads, drives and capacitor banks, a log of stoppages with date and time, bills showing kWh and kvarh, and the distributor's data on interruptions and dips.

Sources and standards

Facing a similar problem in your installation?

Tell us what is happening: we help you work out what to measure, where and for how long, before you change anything in the installation.

Learn more